Company UpdatePress Release / Media Release
Ceigall India Receives Completion Certificate for ₹1,659.84 crore Delhi–Saharanpur Highway Project
Key highlights
- Completion Certificate received for 16.85-km Delhi–Saharanpur NH709B stretch; revised project cost ₹1,659.84 crore.
- Highway forms part of Bharatmala Pariyojana Phase I Economic Corridor; fit for operation since Sept 12, 2024.
- Ceigall to operate and maintain the stretch at ₹2.88 crore per annum, plus escalation.
- Project awarded April 16, 2022; completion extended to August 15, 2024.
- Joint execution with Gayatri Projects Limited.
- Certificate dated Oct 12, 2026; press release issued Oct 13, 2026.