19 Aug 2026 1 filing
Order details
Awarding entity: North Central Railway, Jhansi (domestic).
Nature and scope: Manufacture and supply of 50T EOT Crane with accessories.
Value: Rs. 1,02,15,850 (approx).
Delivery deadline: to be executed by 17 February 2028.
Delivery terms: products to be delivered within the agreed timeline.
Promoter/group interest: No.
Related party transaction: No.
13 Aug 2026 4 filings
Internal Auditor Re-appointment
Re-appointment of M/s. Amit R Aggarwal & Associates as Internal Auditor for FY 2026-27.
Appointed w.e.f. 13 August 2026 for the Financial Year 2026-27.
Firm is a chartered accountants firm providing audit, consultancy, and tax services.
Board approved the re-appointment at its meeting on 13 August 2026.
Disclosure under SEBI LODR Regulations with details in Annexure A.
Deviation and fund utilisation summary
Mode of fund raising: Preferred Issue / QIP.
Fundraising date disclosed.
Amount raised disclosed.
No deviation or variation in use of funds.
Monitoring agency: Not Applicable.
Audit committee: No comments.
Status of fund utilisation: Fully utilised against allocations.
Objects funded: Business expansion, working capital, general corporate purposes.
Original allocations: No variations; funds utilised as planned.
Key disclosures
Board approved unaudited standalone and consolidated results for Q1 ended 30 June 2026.
Limited Review Report of the auditors attached to the results.
Board meeting held on 13 August 2026 from 3:00 PM to 5:00 PM.
Scrip code 522001 and ISIN INE608B01010 mentioned in filing.
Submission to BSE under Regulation 33 of SEBI LODR.
Company Secretary: Heena Sharma (Membership No. A65512).
Financial results approved
Unaudited standalone and consolidated Q1 FY2026-27 results approved for period ended June 30, 2026.
Limited Review Report enclosed; publication planned under Regulation 47.
Internal audit appointment
Re-appointed M/s Amit R Aggarwal & Associates as Internal Auditor for FY2026-27, effective 13 August 2026.
Internal Auditor profile attached as Annexure A.
6 Aug 2026 1 filing
Meeting Details
Date: 13 August 2026
Time: 3:00 PM
Location: Corporate Office, 57/1 Industrial Area Site IV Sahibabad 201010
Key Agenda Items
Consider and approve unaudited standalone and consolidated financial results for Q1 ended 30 June 2026
Consider and approve Limited Review Report from Auditors for Q1 ended 30 June 2026
Other Notes
Trading window remains closed until 48 hours after Q1 2026 results declaration (standalone and consolidated)
20 Jul 2026 1 filing
Order details
NHPC Limited, Chamera Power Station Stage-I, awarded the order.
Upgradation and refurbishment of two 190/30/10 MT EOT cranes CPS-1.
Contract value: INR 5,16,40,000 (about INR 5.164 crore).
Geography: Domestic awarding entity; domestic execution.
Delivery/completion timeline: to be completed by 14 January 2027.
Significant terms: products to be delivered within the agreed timeline.
Related party interest: None; promoter group/related party not involved.
Material impact: No explicit impact disclosed.
18 Jul 2026 1 filing
Order award details
Awarding entity: BHEL PEM – Sunni Dam Hydro Electric Project (domestic).
Nature and scope: Manufacture and supply of DG EOT cranes above 100T.
Order value: approximately ₹10.87 crore.
Execution deadline: delivery by 12 April 2027.
Domestic award; no promoter interest; no related party transaction.
6 Jul 2026 1 filing
Dematerialisation processing and certificate handling
Dematerialisation requests were processed; securities confirmed to depositories and listed on relevant exchanges.
Physical certificates received for dematerialisation were mutilated and cancelled after verification.
Depository name substituted as registered owner within 15 days.