Showing the latest 10 filings. Sign in to filter or browse the full history.
10 of 97 filings·Updated 28 Sept 2026
Showing 10 of 97 filings.
28 Sept 20261 filing
Insider Trading / SASTClosure of Trading Window

G R Infraprojects Ltd trading window closed from 01 October 2026 till 48 hours after the declaration/announcement of the Financial Results for the quarter ending 30 September 2026.

G R Infraprojects Ltd trading window closed from 01 October 2026 till 48 hours after the declaration/announcement of the Financial Results for the quarter ending 30 September 2026.

Filed 18:26View Source
25 Sept 20261 filing
Company UpdatePendency of Litigation(s)/dispute(s) or the outcome impacting the Company

GR Infraprojects: Litigation Update on GST Show Cause Notice

Filing Status

  • GR Infraprojects filed a writ petition against an August 25, 2026 GST show cause notice.
  • Proceedings are pending before the Madhya Pradesh High Court, Indore.
  • Annexure-A discloses the status under Regulation 30 of SEBI LODR.
Filed 13:50View Source
18 Sept 20261 filing
Company UpdateGeneral

NHAI declares appointed date of 7 September 2026 for Agra–Gwalior Greenfield Road project

Appointment and project scope

  • Appointed Date for the project: 7 September 2026; NHAI letter dated 18 September 2026.
  • Project scope: Agra-Gwalior Greenfield Road, 6-lane, DBFOT BOT Toll.
  • Section-1 covers Deori to Susera across UP, Rajasthan, MP.
  • Section-2 overlays on NH-44 from 1058.00 to 1148.00.
  • Estimated project cost: INR 4,262.78 crore (GST-inclusive).
  • Timeline: 910 days from Appointed Date for completion.
  • Mode: DBFOT at BOT Toll under NH(O) scheme.
Filed 17:24View Source
17 Sept 20261 filing
Company UpdateGeneral

GR Infraprojects: NTPC invokes mobilization advance bank guarantee and insurance bonds totaling ₹90.86 crore

Event details

  • NTPC invoked mobilization advance bank guarantee of Rs 49,52,59,040.
  • Three insurance performance bonds totalling Rs 41,33,70,998 were invoked.
  • Total encashment exposure equals Rs 90,86,30,038.
  • Communication received on 17 September 2026.
  • Company terminated related contracts on 15 September 2026.
  • Impact limited to encashed amounts; no material disruption to operations.
Filed 20:49View Source
16 Sept 20261 filing
Company UpdateGeneral

GR Infraprojects terminates NTPC Mouda BESS EPC contracts with immediate effect

EPC termination with NTPC for Mouda BESS

  • GR Infraprojects terminated EPC agreements for Mouda BESS with NTPC, effective immediately.
  • Reason cited: ongoing force majeure, war risk, and contractual issues; disputes invoked.
  • Financial impact of termination is currently being assessed.
  • Execution date of the contracts was 23 April 2026.
  • Parties to the contracts are GR Infraprojects Limited and NTPC Limited.
Filed 19:15View Source
26 Aug 20261 filing
Company UpdatePendency of Litigation(s)/dispute(s) or the outcome impacting the Company

GR Infraprojects faces GST DRC-01 show-cause for Apr 2020-Mar 2021 with Rs 321.60 crore proposed demand

GST Show Cause Notice

  • GR Infraprojects received GST DRC-01 show-cause notice dated Aug 25, 2026.
  • Tax period April 2020 to March 2021; proposed demand Rs 321.60 crore; response being prepared.
Filed 19:29View Source
18 Aug 20261 filing
Company UpdateGeneral

Nagaur-Mukundgarh GST litigation dismissed; exposure ₹69.79 crore; remedies being considered

Litigation status update

  • subsidiary Nagaur Mukundgarh Highways Private Limited filed writ petitions challenging GST on annuity payments.
  • High Court dismissed the petitions on August 17, 2026.
  • Aggregate amount involved is approximately ₹69.79 crore.
  • Company evaluating appropriate legal remedies with its advisors.
Filed 19:46View Source
13 Aug 20261 filing
Company UpdateGeneral

GR Infraprojects receives LOA for MMLP Varanasi PPP project valued at Rs 91.60 crore

LOA for MMLP Varanasi project

  • LOA dated 13 August 2026 from Varanasi MMLP Limited for MMLP Varanasi PPP.
  • Contract value Rs 91.60 crores.
  • Awarded under DBFOT model (Design, Build, Finance, Operate, Transfer).
  • Construction period 1 year from appointed date; concession period 45 years.
  • Awarding entity domestic: Varanasi MMLP Limited.
  • No promoter/promoter group interest in awarding entity.
  • Not a related party transaction.
  • Company will update on further developments.
Filed 17:19View Source
10 Aug 20261 filing
Company UpdateEarnings Call Transcript

GR Infraprojects Q1 FY27: Revenue grows; margins steady; order book at INR 25,300 crore; guidance reaffirmed.

Financial Performance

  • Q1 FY27 standalone revenue INR 2,423 crore; up 32.71% YoY.
  • Consolidated revenue INR 2,784 crore; up 40% YoY.
  • Standalone EBITDA margin 11.01%; YoY decline from 12.17%.
  • Group EBITDA margin 16.8% vs 20% YoY.
  • Standalone PAT INR 203.63 crore; consolidated PAT INR 358 crore; includes INR 46 crore exceptional gain.
  • Standalone net worth INR 9,074 crore; consolidated net worth INR 9,750 crore.
  • Standalone borrowings INR 239 crore; debt-equity 0.03x; consolidated borrowings INR 5,286 crore; 0.55x.
  • Working capital days 148; trade receivables standalone INR 2,655 crore; unbilled revenue 938 crore.

Order Book and Pipeline

  • Order book stands at INR 25,300 crore as of 1 July 2026.
  • Bids worth INR 32,000 crore yet to be opened.
  • Appointed date for three projects totaling INR 7,250 crore awaits.
  • PCOD received for Amritsar Bathinda and Yamuna Bridge projects.
  • Growth strategy includes metro, power, logistics and storage sectors.

Guidance and Outlook

  • FY27 standalone revenue growth guidance around 15-20%.
  • FY28 growth around 20% depending on order inflows.
  • Margin guidance 10-11%; macro factors may cause slight variation.
  • Order inflows guidance around INR 20,000-22,000 crore; +/-10%.
  • Road sector inbound orders targeted around INR 14,000 crore; BOT/HAM mix; capacity 15,000-18,000

Balance Sheet and Liquidity

  • Standalone net worth INR 9,074 crore; consolidated net worth INR 9,750 crore.
  • Standalone borrowings INR 239 crore; debt-equity 0.03x.
  • Consolidated borrowings INR 5,286 crore; debt-equity 0.55x.
  • Fixed-asset additions INR 22 crore; net block INR 1,019 crore.
  • Investments in subsidiaries; HAM/BoT equity INR 3,346 crore; expects INR 900-1,000 crore this year.

Projects and Capex

  • Capex guidance: current year ~INR 300 crore; next year INR 200-250 crore.
  • Agra-Gwalior HAM: appointed date targeted Oct-Nov; other HAMs in December.
  • BharatNet: FY27 revenue around INR 400 crore; O&M around INR 400 crore; total ~INR 1,000 crore.
  • BharatNet ROW delays; O&M started; capex to begin in second half.
  • Warehousing capex deployment ~INR 130 crore; FY27 plan ~INR 450-500 crore.

Q&A Highlights

  • O&G quarterly revenue INR 270 crore; full-year target ~INR 1,000 crore.
  • T&D quarterly revenue ~INR 110 crore; three sectors contribute in Q1.
  • Hydrogen Rail program not pursued; company not exploring that sector.
  • Order inflows target around INR 20,000-22,000 crore; +/-10%.
  • InvIT distributions ~INR 70 crore this quarter; 3-4 assets to InvIT this year.
Filed 18:49View Source
7 Aug 20261 filing
Company UpdateGeneral

GR Infraprojects named successful bidder for MMLP Varanasi PPP project worth Rs 91.60 crore

MMLP Varanasi award details

  • GR Infraprojects declared successful bidder for MMLP Varanasi PPP project.
  • Contract awarded by Varanasi MMLP Limited under DBFOT PPP framework.
  • Total size of the contract is Rs 91.60 crore.
  • Construction period is one year from the appointed date.
  • Concession period extends 45 years from commencement.
  • Domestic entity awarding the contract; no related party involvement noted.
  • Insider trading window to close 48 hours after announcement.